It has been decided to extend LLP Settlement Scheme,2020 scheme till 31st December, 2020.
General Circular No. 31/2O20
F. No. 17/61/2016-CL-V-Pt.I
Government of India
Ministry of Corporate Affairs
"A" Wing, 5th Floor, Shastri Bhawan
Dr. R.P. Road, New Delhi 110001
Date 28th September, 2O20
To
The DGCoA,
All Regional Directors,
All Registrar of Companies,
All Stakeholders
Subject: Extension of LLP Settlement Scheme, 2020
Sir/Madam,
In continuation to this Ministry's General Circular No.13/ 2020 dated 30.03.2020, in view of large scale disruption caused by the COVID-19 pandemic and after due examination, it has been decided to extend aforesaid scheme till 31st December, 2020. All other requirements provided in the said circular shall remain unchanged.
2. This issues with the approval of the competent authority.
Yours faithfully.
(K.M.S. Narayanan)
Assistant Director (Policy)
Copy forwarded for information to:-