This case involves M/s. Sunphoenix Newsprint Pvt. Ltd., a paper mill, which challenged a demand by the local electricity board (TANGEDCO) to produce a safety certificate (CEIG Certificate) before restoring their electricity connection. The court ruled in favor of the company, ordering immediate reconnection of power and giving them three months to submit the required certificate, with a warning that failure to do so would result in disconnection.
Get the full picture - access the original judgement of the court order here
M/s. Sunphoenix Newsprint Pvt. Ltd. vs. The Superintending Engineer, TANGEDCO Distribution, Sivagangai (High Court of Madras)
W.P.(MD)No.3249 of 2025 and W.M.P.(MD)Nos.2260 to 2262 of 2025
Date: 04th February 2025
Should the electricity board (TANGEDCO) insist on the immediate production of a CEIG Certificate before restoring electricity, even after the company has started paying its outstanding dues as per a previous court order?
Petitioner (Paper Mill):
Respondent (TANGEDCO):
Q1: What is a CEIG Certificate?
A: It’s a safety certificate issued by the Chief Electrical Inspector to Government, required for certain electrical installations.
Q2: Why did the court allow reconnection before the certificate was produced?
A: The court considered the business’s compliance with payment orders, the time needed to get the certificate, and the impact on employees and business operations.
Q3: What happens if the company doesn’t submit the certificate in three months?
A: TANGEDCO can disconnect the electricity supply without any further notice.
Q4: Does this mean companies can always delay safety certificates?
A: No. This decision was based on the specific facts of this case, including prior court orders and the company’s compliance with payment terms.
Q5: Was any penalty imposed on the company?
A: No penalty or costs were imposed; the focus was on compliance and business continuity.