Full News

Co. Law, Sebi, Audit & A/c

Madras High Court Orders Power Restoration for Paper Mill, Allows Time for Safety Certificate

Madras High Court Orders Power Restoration for Paper Mill, Allows Time for Safety Certificate

This case involves M/s. Sunphoenix Newsprint Pvt. Ltd., a paper mill, which challenged a demand by the local electricity board (TANGEDCO) to produce a safety certificate (CEIG Certificate) before restoring their electricity connection. The court ruled in favor of the company, ordering immediate reconnection of power and giving them three months to submit the required certificate, with a warning that failure to do so would result in disconnection.

Get the full picture - access the original judgement of the court order here

Case Name

M/s. Sunphoenix Newsprint Pvt. Ltd. vs. The Superintending Engineer, TANGEDCO Distribution, Sivagangai (High Court of Madras)

W.P.(MD)No.3249 of 2025 and W.M.P.(MD)Nos.2260 to 2262 of 2025

Date: 04th February 2025

Key Takeaways

  • The court prioritized business continuity and employee livelihoods by allowing immediate reconnection of electricity.
  • The company must submit the CEIG Certificate (a safety compliance document) within three months.
  • If the certificate is not provided in time, the electricity board can disconnect power without further notice.
  • The judgment balances regulatory compliance with practical business needs.
  • The court enforced its earlier order regarding payment of electricity dues in installments.

Issue

Should the electricity board (TANGEDCO) insist on the immediate production of a CEIG Certificate before restoring electricity, even after the company has started paying its outstanding dues as per a previous court order?

Facts

  • Parties:
  • Petitioner: M/s. Sunphoenix Newsprint Pvt. Ltd. (a paper mill)
  • Respondent: The Superintending Engineer, TANGEDCO Distribution, Sivagangai
  • Background:
  • The company had outstanding electricity dues.
  • In a previous case (W.P.(MD)No.30465 of 2024), the court allowed the company to pay the dues in three installments (Jan–Mar 2025) and ordered reconnection of electricity after the first payment.
  • The company paid the first installment and requested reconnection.
  • TANGEDCO then demanded a CEIG Certificate (a safety certificate from the Chief Electrical Inspector to Government) before restoring power.
  • The company argued that obtaining this certificate would take six months, which would harm their business and employees.

Arguments

Petitioner (Paper Mill):

  • They complied with the court’s earlier order by paying the first installment.
  • They applied for the CEIG Certificate, but it takes about six months to get.
  • Insisting on the certificate before reconnection is unfair and threatens their business and employees’ livelihoods.
  • Requested reconnection now, with a promise to submit the certificate within three months.


Respondent (TANGEDCO):

  • Demanded the CEIG Certificate as a precondition for reconnection, citing safety and regulatory compliance.

Key Legal Precedents

  • Article 226 of the Constitution of India:
  • The writ petition was filed under this article, which empowers High Courts to issue certain writs for the enforcement of rights.
  • Previous Order in W.P.(MD)No.30465 of 2024:
  • The court’s earlier order allowed payment of dues in installments and reconnection after the first payment.
  • No other specific case laws or section/rule numbers are cited in the judgment text provided.

Judgement

  • The court directed TANGEDCO to immediately restore the electricity connection, as the company had paid the first and second installments.
  • The company must submit the CEIG Certificate within three months from the date of the order.
  • If the certificate is not provided within this period, TANGEDCO can disconnect the electricity without further notice.
  • The writ petition was disposed of with these directions, and all related miscellaneous petitions were closed. No order as to costs.

FAQs

Q1: What is a CEIG Certificate?

A: It’s a safety certificate issued by the Chief Electrical Inspector to Government, required for certain electrical installations.


Q2: Why did the court allow reconnection before the certificate was produced?

A: The court considered the business’s compliance with payment orders, the time needed to get the certificate, and the impact on employees and business operations.


Q3: What happens if the company doesn’t submit the certificate in three months?

A: TANGEDCO can disconnect the electricity supply without any further notice.


Q4: Does this mean companies can always delay safety certificates?

A: No. This decision was based on the specific facts of this case, including prior court orders and the company’s compliance with payment terms.


Q5: Was any penalty imposed on the company?

A: No penalty or costs were imposed; the focus was on compliance and business continuity.